AI submittal checks a licensee still marks

AI submittal review compares product data with its specification and lists differences. A licensed architect or engineer marks the action and applies any required seal.

Why the mark and the seal stay with the licensee

  • Preparation The architecture and engineering page treats submittals as preparation: organize the package, suggest a reviewer, and prepare a status summary.

  • Architects In Florida, no registered architect shall seal final documents that were not prepared under that architect's responsible supervising control, or another architect's work that the sealing architect has not reviewed and adopted.

  • Engineers Section 471.025 requires final drawings, specifications, plans, and reports filed for public record, and final documents provided to the owner, to be signed, dated, and sealed by the licensee.

  • Substitution The failure to catch is a quiet substitution the product data never calls out.

Architecture and engineering

From submittal log to a markable review

Run this on one specification division for one project. The submittal log records status, not approval, until a licensed reviewer marks it.

  • Tie to one section The log row names the spec section, the submittal number, and the product.

  • Quote both texts The packet shows the spec words and the product-data words, with page cites.

  • List deviations Where the texts differ, the packet lists a deviation and never calls it acceptable.

  • Leave the action blank Approved, approved as noted, revise and resubmit, and rejected are the reviewer's marks.

  • Draft an RFI response When the spec does not answer the question the product data raises, the packet links an RFI response draft that asks it.

  • Record who marked it The log stores the mark, the date, and the licensee's name.

AI submittal review lines up. The licensee marks.

Comparison is preparation. The mark, the RFI, and any seal belong to the licensee.

  • AI prepares a match of the package to a spec section, quoting both texts.

  • Licensed architect or engineer decides whether that section is the right one.

  • AI prepares a list of differences, and of requirements the product data does not address.

  • Licensed architect or engineer decides which mark each submittal earns.

  • AI prepares a draft RFI question when the spec is silent, without answering it.

  • Licensed architect or engineer decides whether to issue the question and what it asks.

  • AI prepares a submittal log update after a mark is recorded, and never a seal.

  • Licensed architect or engineer decides what to sign or seal, under the state's rule.

Illustrative storefront submittal

  • The spec sentence and the product data are invented They show a finish substitution the log must not hide.

  • Input Spec section for Example Civic Hall: aluminum storefront, Class I anodized finish, color as selected.

  • Output Product data shows a mill finish and names no color. The packet lists both as deviations and leaves the action blank.

  • Note Received is a logistics status, not submittal review. The licensee's mark is the review outcome.

Submittal review checklist before a mark is issued

For the reviewer. It is not a seal and not a substitute for the specification.

  • Log number, spec section, and product name agree, or the mismatch is written out.

  • Each checked requirement quotes the spec and the product data, with a page cite.

  • Requirements the product data does not address stay open, not marked compliant.

  • The reviewer is a licensed architect or engineer for that discipline.

  • No seal, signature, or instrument of service is applied by the workflow.

What the review workflow will not issue

  • Project files stay with that project A detail accepted on one building is not evidence for the next.

  • The workflow will not seal, sign, email the contractor a mark the licensee has not chosen, or treat a logged receipt as approval.

Specification files, the log, and email

  • The categories to connect are the specification set, the submittal log, and the inbox or transfer folder where packages arrive.

  • A pipeline carries the spec sentence and the product-data sentence into one comparison.

Seal and signature rules differ by state. The Florida statutes below are an example because the firm is in Miami. They are not a national rule, and this page is not a professional opinion.

Questions

Can AI submittal review approve a product?

No. It shows where the product data and the spec agree or differ. The approval mark belongs to a licensed architect or engineer, and the log stores it with their name.

When is an RFI response part of submittal review?

When the specification does not answer the question the package raises. If the spec already states the requirement, the packet quotes it instead. An RFI response is never opened to avoid recording a deviation.

Does the submittal log replace the reviewer's mark?

No. Received, forwarded, and under review are logistics. The outcome is the mark stored with the licensee's name, and a log that never records that name has not finished submittal review.

Will this page's Florida statutes apply to a project in another state?

Not as a governing rule. They show how one state ties the seal to the person. The licensee follows the rules of the state where they are sealing.

Start with one workflow